The total mix time ends at the close of the pugmill discharge gate.

Enhance your knowledge for the Asphalt Plant Technician Test with our concise and interactive quiz format. Digest the content through well-structured flashcards and multiple-choice questions, complete with explanations. Ace your exam preparation journey!

Multiple Choice

The total mix time ends at the close of the pugmill discharge gate.

Explanation:
Total mix time is the period during which the materials are being mixed in the pugmill, ending when the discharge gate is closed. Closing the gate stops the mixing and the discharge, so no additional mixing time is counted after that moment. Therefore, the statement is true. This applies to all mixes, not just dry ones, and mixing continues through the discharge phase until the gate is shut, not at the start of discharge.

Total mix time is the period during which the materials are being mixed in the pugmill, ending when the discharge gate is closed. Closing the gate stops the mixing and the discharge, so no additional mixing time is counted after that moment. Therefore, the statement is true. This applies to all mixes, not just dry ones, and mixing continues through the discharge phase until the gate is shut, not at the start of discharge.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy